Works Achieved Year by Year
Works Project Completed 2011
Programmed Works Summer 2011
Common Room Annexe – Create new Head of Years Office
Hill - Internal refurbishment including forming of ground floor rooms and ablutions, new furniture, partitions, doors forming a new social area.
Benson - Installed new addressable fire detection system, raise partitions, install new doors and redecorated where necessary. Formed new opening into dining room and refurbished.
Anglesey - Refurbish and converted toilets and showers. Form new bedroom in private accommodation. Converted two rooms to boarding and final ingoing services to girls house.
Beresford - Covert day boy room to double boarding room and covert single boarding room to single boarding and Single day boy room.
Wellesley - Add extra Pupil spaces on ground floor and additional lockers. Added extra pupils spaces on 1st Floor.
Theatre - Replace Theatre seating and carpets, redecoration, extend and refurbish Theatre Foyer Area.
Introduce sliding folding doors.
House Moves - Planned and coordinated 72 Common Room house moves both on and off College.
Combermere - External painting and minor internal decoration.
Sports Club - Squash Courts, New ceilings, lighting and heating upgrade and two new floors.
Sports Hall - Provide three additional escape doors and roller shutter.
Medical Centre & Apsley - Create five extra boarding rooms, refurbish 1st floor medical rooms.
Create one isolation room.
Hopetoun - Improvements to House kitchen and atrium decoration.
Window Replacements to Staff Housing.
10 other minor works schemes from roofing, stonework.
Library - Formed temporary Library in Old Hall, Library and Selangor Court project started.
Completion Selangor Court end of February, Library end of March 2012.
BOARDING HOUSE INSPECTION REPORT 2011/2012
|
Department |
Date |
Fabric |
Furniture |
Cleanliness |
Health & Safety |
Fire Safety |
General ConditionComments & Action |
ActionPlan Year |
|
Anglesey |
02/11/2011 |
4 |
3 |
3 |
3 |
3 |
Potential number increase 2012/2013 leading to Assistant H/M accommodation extension (Driven by Pupil numbers) |
2012/2013 £270K |
|
Apsley |
16/02/2011 |
5 |
5 |
4 |
3 |
3 |
Additional Boarding link over Medical Centre adding 5 extra Boarding spaces completed. Minor Works to utility area. |
2012/2013/2014 £35K |
|
Benson |
09/11/2011 |
4 |
2 |
4 |
4 |
5 |
Extra III Form shower block on Ground Floor. Ablution refurbishment and Furniture replacement 2013/2014 |
2015 £200K |
|
Beresford |
08/12/2010 |
3 |
3 |
3 |
3 |
3 |
Starting to look tired. Day & boarding additions 2011. Part Internal decorations to freshen Summer 2013 |
2013 £30K |
|
Blucher |
09/02/2011 |
4 |
4 |
3 |
3 |
3 |
Internal Decoration to circulation areas to maintain standards Summer 2013 (£36K) |
2013 £36K |
|
Combermere |
10/03/2010 |
4 |
4 |
4 |
3 |
3 |
Some Internal Decorations completed 2011 Further Internal Decorations 2013 |
2013 £30K |
|
Hardinge |
02/03/2011 |
4 |
4 |
4 |
3 |
3 |
No Planned Action. Projected Internal Decorations 2019 |
2019 £30K |
|
Hill |
02/02/2011 |
5 |
5 |
5 |
4 |
4 |
Full Internal Refurbishment Completed Summer 2011 Projected Internal Decorations 2016 |
2016 £30K |
|
Hopetoun |
12/01/2011 |
3 |
3 |
4 |
4 |
3 |
Upgraded & Modified Kitchen, Atrium Decoration Completed 2011. Internal Redecoration and Furniture Refurbishment Decoration to Internal Block work £60K, Furniture Re-fit £175K, Flooring £15K. |
2016 £250K |
|
Lynedoch |
07/03/2011 |
2 |
2 |
3 |
3 |
3 |
Ablutions Refurbishment, Furniture Refit, Wall Cladding, Re-Order Social Space, Kitchen & House Matrons Office. |
2012 £250K |
|
Murray |
26/01/2011 |
3 |
2 |
3 |
3 |
3 |
Full Internal Refurbishment |
2014 £220K |
|
Orange |
19/01/2011 |
4 |
4 |
4 |
3 |
3 |
No Action Projected Internal Decorations 2017 |
2017 £30K |
|
Picton |
16/03/2011 |
3 |
3 |
4 |
3 |
3 |
No Action, Minor Maintenance, some touch up of decoration. Extra Boarding will require building an extension (Driven By Pupils Numbers) |
TBA £750K |
|
Stanley |
15/12/2010 |
3 |
3 |
4 |
3 |
2 |
Major maintenance, toilets, partitions, fire doors and detection. |
2013 £300K |
|
Talbot |
23/03/2011 |
3 |
3 |
3 |
3 |
3 |
Ablution Flooring Replacement 2012 |
2012 £10K |
|
Wellesley |
30/03/2011 |
4 |
4 |
4 |
3 |
3 |
Additional day pupil’s furniture 2010 100% Projected Internal Decorations |
2021 £30K |
|
Raglan |
27/04/2011 |
3 |
3 |
3 |
3 |
3 |
Kitchen & Social Improvements and some Internal redecoration. Projected Internal Decorations. |
2017 £30K |
Works Projects Completed Summer 2010
Forming of the 6th Form Social Room in the Hill
External painting of the Hill
New Office formed, New Lockers and Desks in the Raglan
Refurbishment Common Room
Redecoration of the Medical Centre
Remodelling - Female Accommodation (Showers) Common Room, Hill and Murray
94 Accommodation Moves, On and off site (including new rentals) for additional staff
New Doorway between Dining Room and Waterloo Room adding additional dining spaces
Building a Orangey on the Orange creating additional social areas
Creating a extension on the Wind Annex Music Tech Suite
Anglesey phase 2/3 girls
New Paving to the Bursary Quad
Extra boarding and day place formed in the following Boarding Houses: Orange, Beresford, Hardinge, Picton, Talbot, Apsley, Murray, Benson, Raglan & Murray
Converted Jupiter Suite to PR Class Room
Created the Apsley Link
Extra Classrooms in Modern Languages
Ablutions Refurbishment in the Hill & Lyndeoch
Office Moves College office, Admin support, International Director moved & Head of Years
BIT’s classroom changed to Art Classroom
Improvement works:- Ceiling, Lighting & Redecoration in the Queens Court Green Room
Office Remodelling Queens Court Theatre
Major Boiler Works to the following Boarding Houses and Classrooms:- Hill, Lynedoch, Murray, East Block and Queens Court
BOARDING HOUSE INSPECTION REPORT 2010/11
|
Department |
Date |
Fabric |
Furniture |
Cleanliness |
Health & Safety |
Fire Safety |
General ConditionComments & Action |
ActionPlan Year |
|
Anglesey |
17/11/2010 |
3 |
3 |
4 |
3 |
3 |
Phase 2 & 3 Girls. All girls’ house 2011 60 pupils with assistant H/M house extension. |
2010/2011 |
|
Apsley |
16/02/2011 |
5 |
5 |
4 |
3 |
3 |
Extra boarding 2010. Link between H/M and Boarding House Summer 2010 |
|
|
Benson |
24/11/2010 |
3 |
2 |
4 |
3 |
2 |
Replace fire detection system, fire doors and partition. |
2011/2012 |
|
Beresford |
08/12/2010 |
3 |
3 |
3 |
3 |
3 |
Starting to look tired. Extra boarders 2010. |
|
|
Blucher |
09/02/2011 |
4 |
4 |
3 |
3 |
3 |
Decoration starting to show wear and tear. |
|
|
Combermere |
10/03/2010 |
4 |
4 |
4 |
3 |
3 |
Still in very good condition but decoration showing signs of wear and tear. |
No action |
|
Hardinge |
02/03/2011 |
4 |
4 |
4 |
3 |
3 |
Remove apartment to form extra boarding spaces. |
2010 |
|
Hill |
02/02/2011 |
2 |
2 |
3 |
3 |
2 |
Ablution work make over and part decoration, fire detection upgrade |
2010 |
|
Hopetoun |
12/01/2011 |
3 |
3 |
4 |
4 |
3 |
All girls house working well with minor issues. Boarding furniture well worn. |
|
|
Lynedoch |
07/03/2011 |
2 |
2 |
3 |
3 |
3 |
Ablutions make over 2010, Shower & bath 2011. |
2010/2011 |
|
Murray |
26/01/2011 |
3 |
2 |
3 |
3 |
2 |
No fire evacuation reports issued by H/M. Ablution works 2011. Brew room upgrade 2011/ 2012 |
2011/2012 |
|
Orange |
19/01/2011 |
4 |
4 |
4 |
3 |
3 |
Orange extension to facilitate 6 extra Boarders. |
010 |
|
Picton |
16/03/2011 |
3 |
3 |
4 |
3 |
3 |
One extra boarders. |
2010 |
|
Stanley |
16/12/2009 |
3 |
3 |
4 |
3 |
2 |
Major maintenance, toilets, partitions, fire doors and detection. |
2010/2012 |
|
Talbot |
23/03/2011 |
3 |
3 |
3 |
3 |
3 |
Still in very good serviceable condition. No issues to report. Two extra boarders. |
2010 |
|
Wellesley |
30/03/2011 |
4 |
4 |
4 |
3 |
3 |
Additional day pupil’s furniture 2010. |
No Action |
|
Raglan |
27/04/2011 |
3 |
3 |
3 |
3 |
3 |
Additional day pupil’s furniture for 2010 & 2012. |
No further action |
Condition Key: 5 = BRAND NEW/REFURBISHED 4 = VERY GOOD 3 = GOOD 2 = FAIR/SERVICEABLE 1 = POOR
Works Projects Completed 2009 /2010
During this last year the following schemes have been completed.
The Monro Pavilion.
The Apsley Refurbishment – Heating, Furniture, Redecoration, Power and IT.
Anglesey - Phase 1 girl’s ingoing service.
Murray Nursery Link - Additional pupil spaces (12).
Hopetoun - Additional pupil spaces (8).
SLT and Admin Office movements.
Classroom reorganisations plus installing Harkness Tables.
65 Staff Housing movements.
Toilet facilities refurbishment.
BOARDING HOUSE INSPECTION REPORT 2009/2010
|
Department |
Date |
Fabric |
Furniture |
Cleanliness |
Health & Safety |
Fire Safety |
General ConditionComments & Action |
ActionPlan Year |
|
Anglesey |
18/11/2009 |
3 |
3 |
4 |
3 |
3 |
Phase 2 & 3 Girls. All girls’ house 2011 60 pupils with assistant H/M house extension. |
2010/2011 |
|
Apsley |
24/02/2009 |
5 |
5 |
4 |
3 |
3 |
Extra boarding 2010. Link between H/M and Boarding House Summer 2010. |
|
|
Benson |
25/11/2009 |
3 |
2 |
4 |
3 |
2 |
Replace fire detection system, fire doors and partition. |
2011/2012 |
|
Beresford |
02/12/2009 |
3 |
3 |
3 |
3 |
3 |
Starting to look tired. Extra boarders 2010. |
|
|
Blucher |
10/02/2010 |
4 |
4 |
3 |
3 |
3 |
Decoration starting to show wear and tear. |
|
|
Combermere |
10/03/2010 |
4 |
4 |
4 |
3 |
3 |
Still in very good condition but decoration showing signs of wear and tear. |
No action |
|
Hardinge |
03/03/2010 |
4 |
4 |
4 |
3 |
3 |
Remove apartment to form extra boarding spaces. |
2010 |
|
Hill |
21/01/2010 |
2 |
2 |
3 |
3 |
2 |
Ablution work make over and part decoration, fire detection upgrade |
2010 |
|
Hopetoun |
13/01/2010 |
3 |
3 |
4 |
4 |
3 |
All girls house working well with minor issues. Boarding furniture well worn. |
|
|
Lynedoch |
08/03/2010 |
2 |
2 |
3 |
3 |
3 |
Ablutions make over 2010, Shower & bath 2011. |
2010/2011 |
|
Murray |
27/01/2010 |
3 |
2 |
3 |
3 |
2 |
No fire evacuation reports issued by H/M. Ablution works 2011. Brew room upgrade 2011/ 2012 |
2011/2012 |
|
Orange |
18/01/2010 |
4 |
4 |
4 |
3 |
3 |
Orange extension to facilitate 6 extra Boarders. |
2010 |
|
Picton |
17/03/2010 |
3 |
3 |
4 |
3 |
3 |
One extra boarders. |
2010 |
|
Stanley |
16/12/2009 |
3 |
3 |
4 |
3 |
2 |
Major maintenance, toilets, partitions, fire doors and detection. |
2010/2012 |
|
Talbot |
24/03/2010 |
3 |
3 |
3 |
3 |
3 |
Still in very good serviceable condition. No issues to report. Two extra boarders. |
2010 |
|
Wellesley |
28/04/2010 |
4 |
4 |
4 |
3 |
3 |
Additional day pupil’s furniture 2010. |
No Action |
|
Raglan |
28/04/2010 |
3 |
3 |
3 |
3 |
3 |
Additional day pupil’s furniture for 2010 & 2012. |
No further action |
Condition Key: 5 = BRAND NEW/REFURBISHED 4 = VERY GOOD 3 = GOOD 2 = FAIR/SERVICEABLE 1 = POOR
Works Projects Completed 2008 – 2009.
During this last year one of the largest building refurbishment programmes has delivered in the college’s history. This included.
The Wellesley - Girl’s Day House.
The Hardinge - Boy Sixth Form Boarding House.
Modern Languages
V & A Social Café
Queens Court Internal Transformation.
BOARDING HOUSE INSPECTION REPORT 2008/2009
|
Department |
Date |
Fabric |
Furniture |
Cleanliness |
Health & Safety |
Fire Safety |
General ConditionComments & Action |
ActionPlan Year |
|
Anglesey |
19/11/2008 |
3 |
3 |
4 |
3 |
3 |
Phase girls. Kitchen upgrade. |
2009/2010 |
|
Apsley |
25/02/2009 |
3 |
3 |
3 |
3 |
3 |
Heating system replacement. Replace furniture, carpets and lighting upgrade. |
2009 |
|
Benson |
12/11/2008 |
3 |
2+ |
4 |
3 |
3 |
Additional boarding spaces plus kitchen remodel. |
2009 |
|
Beresford |
26/11/2008 |
3+ |
3+ |
3+ |
4 |
4 |
Some internal decoration. |
2010 |
|
Blucher |
11/02/2009 |
2+ |
4 |
3/4 |
3 |
3 |
Some internal decoration. |
2010 |
|
Combermere |
11/03/2009 |
4+ |
4+ |
4 |
4 |
4 |
In very good condition. |
|
|
Hardinge |
06/05/2009 |
5 |
4 |
4 |
4 |
4 |
Newly refurbished 2008 |
|
|
Hill |
02/03/2009 |
2+ |
2+ |
3 |
4 |
4 |
Minor maintenance items required Brew Rooms and Ablutions. |
2009/2010 |
|
Hopetoun |
07/01/2009 |
3 |
3 |
3+ |
3 |
3 |
Girl’s final phase plus additional boarding. |
2009/2010 |
|
Lynedoch |
02/02/2009 |
2+ |
2+ |
3 |
2+ |
2+ |
Minor improvements, raising partitions and Fire detection. |
2009/2010 |
|
Murray |
29/01/2009 |
2+ |
2 |
3 |
3 |
3 |
Extra boarding with link to Murray. |
2009/2010 |
|
Orange |
04/02/2009 |
4 |
4 |
4 |
3 |
3 |
In very good condition no action required. |
|
|
Picton |
18/03/2009 |
3+ |
3+ |
4 |
4 |
4 |
In good condition, no action. Scheme to add 10 extra boarders designed. |
2010/2011 or 2011/12 |
|
Stanley |
14/01/2009 |
4 |
4 |
4 |
3 |
4 |
This house is working very well no planned action. |
|
|
Talbot |
03/12/2008 |
3+ |
3+ |
3+ |
4 |
4 |
In good condition no action. |
|
|
Wellesley |
29/04/2009 |
5 |
4+ |
4+ |
4 |
4 |
Opened in 2008 no action. |
|
|
White Cairn |
22/04/2009 |
4+ |
4+ |
4 |
4 |
4 |
In good condition. The new Matron and support team are making a difference. |
|
Condition Key: 4 = VERY GOOD 3 = GOOD 2 = FAIR/SERVICEABLE 1 = POOR
Works Projects completed 2007 – 2008
Combermere - Girls Boarding House which was delivered on time and budget. A major transformation from two boys houses to one girl which has been well received.
White Cairn - Boys Day House, following a major extension adding 50% to the floor area the building was opened on time and budget ready for Sept 2007.
Wellesley - introduced a Girls Day House in to the East Block (Formally Beresford) as the first intake.
Hopetoun - Created year one girls secure facility which in practice has worked very well.
QCA (Queens Court Annex) - completed the construction of 12 x 50m2 classrooms plus supporting facilities on time and budget.
IB Suite - In support of IB the ground floor of the East Block was formed with offices and seminar room.
Kitchen Servery – During the summer of 2007 the Servery was remodelled into a free flow system.
General - We also delivered a range of other projects such as managing 63 staff housing moves, office moves and other facilities such as the Road and Building Lighting scheme water main repairs, Electrical and Fire Detection and Safety Measures.
BOARDING HOUSE INSPECTION REPORT 2007/2008
|
Department |
Date |
Fabric |
Furniture |
Cleanliness |
Health & Safety |
Fire Safety |
General Condition/Comment/Action |
ActionPlan Year |
|
Anglesey |
21/11/2007 |
2 |
2 |
23 |
3 |
3 |
House in good condition. TV room furniture update. Redesign kitchen. Girls Phase 1 2009. Hard play area 2009/2010. |
2008/2009 |
|
Apsley |
27/02/2008 |
3 |
3 |
4 |
3 |
3 |
The house is being managed to a very good Standard. No letts planned 2009 to enable mechanical upgrade, toilets & showers. Create computer room. |
2009/2010 |
|
Benson |
14/11/2008 |
3 |
3 |
4 |
4 |
4 |
The house is in good condition and very clean. Works forward planning. Hard play area 2008/2009. Ablutions upgrade 2009, partition furniture upgrade 2010/2011. |
2008/2009 2010/2011 |
|
Beresford |
28/11/2008 |
3+ |
3+ |
3+ |
3 |
4 |
More sofas, some minor decoration overall very good order. |
No Major Action. |
|
Blucher |
05/03/2008 |
3+ |
3+ |
4 |
4 |
4 |
Third form showing signs of ware and tear. House in very good order. |
No Major Action. |
|
Combermere |
19/03/2008 |
4+ |
4+ |
4 |
4 |
4 |
First inspection, house in very good condition. Some extra furniture required. |
2008/2009 |
|
Hardinge |
06/02/2008 |
3 |
2+ |
3 |
3 |
3 |
The house is in good serviceable condition. The house is to be refurbished and refurnished summer 2008. |
2008 |
|
Hill |
23/01/2008 |
3 |
3 |
3 |
3 |
3 |
One of the older houses which is being managed and maintained in good order. Long term refurbishment planned. |
2009/2011 |
|
Hopetoun |
09/01/2008 |
3 |
3 |
4 |
2+ |
3 |
The house is managed to a good standard. Girls Phase 1 working well. Phase 2 for Sept 2008 re carpet and furniture. |
2009/2010 |
|
Lynedoch |
23/01/2008 |
3 |
3 |
3+ |
4 |
3 |
Part of West Block planned re-order 2009/2011. Well managed and good standard throughout. |
2009/2011 |
|
Murray |
30/01/2008 |
2 |
2 |
2+ |
3 |
3 |
House looking tired, decretive makeover required. Extra pupil spaces 2008. House is part of West Block re-order plans. |
2008 2009/2011 |
|
Orange |
12/03/2008 |
4 |
4 |
4 |
4 |
4 |
Very good in all areas. |
No Action. |
|
Picton |
19/03/2008 |
3+ |
3+ |
3 |
3 |
3 |
Managed and maintained to a good standard. Consider extension to add 10 extra pupils. |
2009/2010 |
|
Stanley |
16/01/2008 |
4 |
3+ |
4 |
4 |
4 |
A number of minor maintenance and improvements plus arranged for additional pupils. Long term, partitions and furniture upgrade. Excellent standard. |
2010/2011 |
|
Talbot |
28/11/2007 |
3+ |
3+ |
3+ |
3 |
3 |
Very good standard not action required. |
No Action. |
|
Wellesley |
06/02/2008 |
3 |
3 |
3 |
3 |
3 |
This house has worked very well as our first Girls Day House. Well managed. |
No Action. |
|
White Cairn |
13/02/2008 |
4 |
4 |
4 |
3 |
4 |
House in very good condition. Extra furniture and parking for Sept 2008 as house will be full. |
2008/2009 |
Condition Key: 5 = BRAND NEW/ REFURBISHED 4 = VERY GOOD 3 = GOOD 2 = FAIR/SERVICEABLE 1 = POOR